top of page

January 2022 Project update for Sanctuary of Love Centre (Centre du Sanctuaire de l'Amour)

  • In November 2021, the land purchase was finally approved by the Senegalese Government, nearly two years after we purchased it!

  • In December 2021, a well was dug (by hand!), and miraculously water was discovered only 25 feet down. This is a gift from God!

  • A perimeter fence surrounding the 3.6-acre property is being started in January 2022. Estimated completion: April 2022. This project will employ several local men.

  • As of October 2022, the fence is 95% of the way complete with only 200 feet remaining. 

Our team is planning, God willing, to start construction of the Sanctuary of Love Centre in 2022. The construction will advance as donations are received. We are a non-denominational, non-profit, independent ministry. We were founded on faith and prayer and are supported by friends and family who have a heart for the vulnerable Senagalese children. Please join us in prayer and thank you for giving financially as you feel led.

bottom of page